Bailey Off-Site rises to the occasion

NG Bailey is lowering into place the first of 14 prefabricated modules at Heathrow airport's Terminal 5 to supply all low temperature hot and cold water and domestic services to the new terminal.
Bailey Off-Site rises to the occasion
The four core risers being erected at Heathrow are commissioned by Carillion and manufactured by Bailey Off-Site.

Each of the four core risers are 25m tall with a 24m2 footprint. They will house all main ductwork runs.

The company says the use of off-site manufacturing has resulted in a lot of time being saved - four months per riser, when compared with traditional methods.
18 May 2009

Comments

Already Registered?
Login
Not Yet Registered?
Register

New BESA guidance will ‘revolutionise building air quality’

The Building Engineering Services Association (BESA) has launched a new specification for ventilation hygiene as part of its ongoing efforts to minimise the risk posed by contaminated indoor air to human health and well-being....

  18-Apr-2024
ACR News

Vapac Electrode Boiler launched

As the exclusive Vapac distributor in the UK, Humidity Solutions has announced the launch of the NEW Vapac Electrode Boiler, which incorporates advanced technology to minimise water and energy wastage....

  18-Apr-2024

STOKVIS R600

CONDENSING ULTRA LOW NOx PREMIX COMMERCIAL BOILER
  10-Jan-2019
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

HVR Awards 2024
https://www.heatingandventilating.net/bailey-off-site-rises-to-the-occasion