NG Bailey is lowering into place the first of 14 prefabricated modules at Heathrow airport's Terminal 5 to supply all low temperature hot and cold water and domestic services to the new terminal.
Bailey Off-Site rises to the occasion
The four core risers being erected at Heathrow are commissioned by Carillion and manufactured by Bailey Off-Site.

Each of the four core risers are 25m tall with a 24m2 footprint. They will house all main ductwork runs.

The company says the use of off-site manufacturing has resulted in a lot of time being saved - four months per riser, when compared with traditional methods.
18 May 2009

Comments

Already Registered?
Login
Not Yet Registered?
Register

Heating installers preparing to seize Net Zero opportunity

Plumbing and heating installers see the drive to reduce emissions as an opportunity, and are optimistic about the short and long-term future of their businesses, according to new research released today....

  26-Oct-2021

CIAT heat pumps power river source renewable energy project for fruit grower

High efficiency CIAT heat pumps have been chosen to power a major 8.8MW river-source renewable energy project in the South of England to help produce more fruit. CIAT is part of Carrier Global Corporation, the global provider of healthy, safe, ...

  26-Oct-2021

If you need to open a Solenoid Valve manually, you need a SVOM!

If you need to open a Solenoid Valve manually, you need a SVOM!
  22-Oct-2021
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

BESA National Conference – Virtual event