Bailey Off-Site rises to the occasion

NG Bailey is lowering into place the first of 14 prefabricated modules at Heathrow airport's Terminal 5 to supply all low temperature hot and cold water and domestic services to the new terminal.
Bailey Off-Site rises to the occasion
The four core risers being erected at Heathrow are commissioned by Carillion and manufactured by Bailey Off-Site.

Each of the four core risers are 25m tall with a 24m2 footprint. They will house all main ductwork runs.

The company says the use of off-site manufacturing has resulted in a lot of time being saved - four months per riser, when compared with traditional methods.
18 May 2009

Comments

Already Registered?
Login
Not Yet Registered?
Register

One in five building service engineers unfamiliar with overheating regulations

New research has revealed that 20% of building service engineers are unfamiliar with the UK Building Regulations’ Approved Document O, which addresses overheating in buildings – and almost half (46%) claim to understand the theory behind it but are ...

  25-Jul-2024

Carbon reductions for northern arena

Rinnai hot water systems are projected to produce ‘significant’ carbon reductions at a huge indoor arena in the North of England. The company has produced a designed system based on its R290 high-temperature heat pump. This arena regularly hosts large events such as concerts, conferences, theatre plays, exhibitions, live music and other conventions – so the site must have an energy efficient and carbon-reducing hot water system to achieve NetZero. 

  25-Jul-2024

STOKVIS R600

CONDENSING ULTRA LOW NOx PREMIX COMMERCIAL BOILER
  10-Jan-2019
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

HVR Awards 2024