Tyre production stopped in tracks by boiler breakdown

TYRE production has ground to a halt at Pirelli's UK tyre factories because of a boiler malfunction.
Maintenance engineers worked through the August bank holiday weekend to try to repair a boiler at the firm's tyre factory in Carlisle, but Pirelli bosses are still waiting for the plant to get back to the business of making tyres.

The failure of one of Pirelli's Carlisle factory boilers, resulted in Pirelli stopping production at both its UK plants. Pirelli's other UK factory in Burton was forced to shutdown because it supplies the raw materials for tyre production at the Carlisle plant.

The boiler fault was discovered last Thursday (August 21) and workers were told to stay away from the factory. Pirelli is currently getting all boilers at the giant Carlisle plant inspected.

A spokesman for Pirelli said the cause of the boiler fault was still being investigated.

The Pirelli factory, which employs about 1,000 workers, usually operates around the clock for 365 days a year.

The shutdown of the factories has resulted in the lost production of thousands of tyres.
26 August 2008

Comments

Already Registered?
Login
Not Yet Registered?
Register

UK radiator manufacturers and distributors required to comply with BS-EN442

As part of its ongoing efforts to uphold legal standards and ensure transparency in product performance and advertising claims across the sector, the Manufacturers' Association of Radiators and Convectors (MARC) has issued a reminder that all ...

  21-Oct-2025

Stainless Steel Indirect Cylinders – The Foundation Of Sustainable DHW

A plant room-based hybrid approach, which separates heat sources from the water storage, remains the most cost-effective, proven method for obtaining low-carbon water heating in commercial buildings. These systems deploy renewable or low-carbon ...

  15-Oct-2025

STOKVIS R600

CONDENSING ULTRA LOW NOx PREMIX COMMERCIAL BOILER
  10-Jan-2019
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

https://www.heatingandventilating.net/tyre-production-stopped-in-tracks-by-boiler-breakdown-