Fire at Calorex destroys 20% of production

Calorex Heat Pumps says it will be back in full production within weeks after a fire completely destroyed one of three buildings at its UK headquarters.
The blaze at Calorex HQ in Maldon, Essex, destroyed 20% of the heat pump supplier's manufacturing capacity with one third of its total warehousing facilities lost.

Production in the main factory resumed on February 22. Within a week a nearby warehouse was rented to replace the lost facilities.

No one was injured.

A spokesman for Calorex said:'The 140-strong workforce was briefed on the day after the fire and told that it was Calorex's expectation there would be no job losses as a result of this first ever fire loss in the company's 34-year history'.

Calorex management confirmed it will continue to manufacture its range of heat pumps and dehumidifiers in Maldon.

'We want to assure our customers that lead times will be maintained' said Richard Carrington, Calorex managing director.
5 March 2010

Comments

Already Registered?
Login
Not Yet Registered?
Register

UK heat pump sales reach record high in 2025, but more must be done to meet targets

New data published by the Heat Pump Association UK shows that heat pump sales reached another record high in 2025, with over 125,000 units sold in the UK, a 27% increase on the previous year....

  17-Feb-2026

Fernox to exhibit at MOSTRA CONVEGNO EXPOCOMFORT 2026

Leading water treatment company, Fernox, is pleased to be exhibiting at Mostra Convegno Expocomfort (MCE) 2026 in Milan, Italy. Taking place 24th- 27th March, Fernox will showcase its comprehensive range of chemical water treatment solutions for ...

  17-Feb-2026

STOKVIS R600

CONDENSING ULTRA LOW NOx PREMIX COMMERCIAL BOILER
  10-Jan-2019
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

HVR Awards 2026