Know what you want? Try our 'Supplier Directory' 

New heating system keeps priceless treasures warm and dry

Harrow, London-based mechanical services contractor G & D Higgins has marked its 20th year in business by completing a major boiler replacement and heating system upgrade at The British Library, St Pancras, a complex project that turned out to be a text book operation.
New heating system keeps priceless treasures warm and dry
Not surprisingly, with such treasures as the Magna Carta, Leonardo da Vinci's original notebook, The Times first edition - dated March 18, 1788 - and Beatles' manuscripts in its care, The British Library demanded the quality of services within its flagship building – essential heating and dehumidification - be maintained throughout.

With a reduction in the building's carbon footprint firmly in view, the Library project included replacement of two non-condensing 1.75MW output steel boilers used for space heating during the winter and dehumidification re-heat during the summer months. These in turn served plate heat exchangers on the building's very low temperature hot water circuit.

As replacements, three 600kW output Ygnis boilers, complete with Dunphy fully modulating natural gas burners offering maximum turndown with efficiency, were specified and installed by the G & D Higgins team.

They had to make judicious use of branch connections in order to maintain existing plant load throughout the 112,000m2 floor area building during what turned out to be a continually cold winter period.

Further savings were achieved with the inclusion of an Ygnis Totelco extractive economiser within the flue that is common to all three boilers.

With the total system firing on its high rate, a maximum recovery here of 50kW is expected from capturing this otherwise wasted heat.

Optimisation of the heating system to more closely match today's use of the '80s building also involved G & D Higgins in considerable resizing and replacement of complex pipework to create further savings by reducing pumping loses throughout.

Replacement of two gas fired storage water heaters with two Aquasave BIO hot water heaters on the separate, variable low temperature hot water circuit was also undertaken.

According to Chris Denman, senior mechanical engineer at The British Library, G & D Higgins, working under design consultant Primeglen Design Limited, impressed from the outset.

'Director David Higgins brought the right people to the site for the very first meeting. He showed that he knew what he was talking about from the beginning, that he understood the job and the risks, and he knew why we had to keep the building going for seven days per week, throughout the turnkey contract.'

Relative humidity levels are critical, particularly within the four basements of the Library that extend to a depth of 24.5metres and where air has to be chilled, its moisture reduced then reheated. Often the heating load within the building can be greater in the summer.
24 September 2010

Comments

Already Registered?
Login
Not Yet Registered?
Register

FETA welcomes guests to Annual Luncheon

The 2024 FETA Annual Luncheon took place on Thursday 11th April and attracted guests from across the heating, ventilation, building controls, refrigeration and air conditioning industries as well as individuals from related institutions, ...

  25-Apr-2024

Prizes galore to be won on Conex Bänninger’s interactive stand

Conex Bänninger, a global leader in the manufacture of high-quality fittings, valves and accessories, will have an enhanced interactive stand (5D19) at InstallerShow 2024....

  25-Apr-2024

STOKVIS R600

CONDENSING ULTRA LOW NOx PREMIX COMMERCIAL BOILER
  10-Jan-2019
Heating & Ventilating Review is the number one magazine in the HVAR industry. Don’t miss out, subscribe today!
Subcribe to HVR

Diary

HVR Awards 2024